Resource load levelling within multiple projects
- Created
- 3
- 3
Hi all,
I have a query relating to load levelling resources within multiple projects with differing priorities.
I know a project has a "Project Levelling Priority" function within P6, so you can level using "Level Resources" that way; however, my schedules are set up using work packages at WBS level within multiple projects. Would it be possible to load level across multiple projects at WBS level?
So for example:
Resource 1
Priority 1 - WP2, Project A
Prioity 2 - WP4, Project B
Priority 3 - WP1, Project A
Resource 2
Priority 1 - WP5, Project C
Priority 2 - WP3, Project B
Priority 3 - WP3, Project A
As you can see, performing a "global" load levelling using the priorities wouldn't really help. Does anyone have a possible solution please? Many thanks in advance.
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?