Compensation Events

James ParkerMember for 14 years
Created
1
3
0

Hi all

 

Apologies if this has aready been asked / answered.

Can anyone guide me in the best direction on how to schedule compensation events into the project baseline? Im working under the NEC contract.

Thanks 

James

1 reply

Oldest first
  1. 0
    Mike Testro ·

    Hi JamesIt is the same method

    Hi James

    It is the same method as described in an Impacted as Planned delay analysis method.

    1. Calculate the duration of the compensation event.

    2. Set this into a Sub Chart.

    3. Link to the affected task(s).

    4. Hit F9 and wait for the howls of protest from the CA.

    Best regards

    Mike Testro