Can you limit number of activities on a day?

Philip AttersalMember for 10 years 8 months
Created
2
4
0

Hi All

Firstly. I am a lvl 3 planner. And a new one at that. More used to reviewing contractors programmes, than building ones...

So. Question 

I am building a programme, where upon only we have a deliverable to be discussed at a weekley meeting

Problem is. We only have two meetings a week. And can only discuss so many deliverables per meeting

If I create a new calender for the meetings, can I create a 'rule' of some king. Ie. If more than 3 deliverables are forecast to the meeting, it will jump to the next one?

 

Regards

Philip 

2 replies

Oldest first
  1. 0
    Mike Testro ·

    Hi PhilipIn most programmes

    Hi Philip

    In most programmes you can put in a resource levelling system on your deliverable resource - allowing only 2 per week.

    Best regards

    Mike Testro

  2. 0
    Philip Attersal ·

    Thank you. Just need to work

    Thank you. Just need to work out how to do that. I've never used resources in P6 

    Bit of trial and error :-) 