Activities starting at the end of the shift

Kevin RaynerMember for 17 years 9 months
Created
2
1
0

A couple on months ago somebody at work corrupted the most used calendar in the database. This has been rectified but I am now finding activities starting an the end of a shift rather than the start of the shift on the next day.

I cant see why if the shift ends at 16.00 why the successor with an FS link is starting at 16.00 and not 08.00 the next day.

2 replies

Oldest first
  1. 0
    Kevin Rayner ·

    Fixed now. the calendar had

    Fixed now. the calendar had been incorrectly amended.

  2. 0
    Zoltan Palffy ·

    make sure that the activities

    make sure that the activities are assigned to the correct calendar 