Resource allocation practice

Lazy BookwarmMember for 9 years 8 months
Created
4
3
0

Hi,

My programme consists of huge excavation / area grading work for which we are going to use 6 excavators. We have divided the whole area in 6 parts and excavation gonna start in all the areas at same time, hence consurrent work. So in the programme I have to assign resources to these activities. So among the following which is the best practice:

1) create and assign a generic resource called Excavator to all the concurret activities which will show overallocation of resources

2) create resources Excavator 1, Excavator 2 , Excavator 3......, Excavator 6 and assign to relevant activity which will not show overallocation.

Please recommend which one shall be used.

Thanks.

4 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    I would choose #1 not only to

    I would choose #1 not only to show the over utilization but to know when you can remove one or more of the excavators off site. Paying for rental or being idel on a project is a wste of money. Send that unused excavator off site to another project to stop the charges. 

  2. 0
    Lazy Bookwarm ·

    Our client doesn't want to

    Our client doesn't want to see overallocated resources in the programme. So that's why I wanted to know the standard practice in the industry, wheather it is common to show overallocated resources in the programme or not. 

  3. 0
    Vladimir Liberzon ·

    I don't understand your

    I don't understand your problem.

    You can enter the number of available excavators and level your schedule.

     

  4. 0
    Zoltan Palffy ·

    then just turn the over

    then just turn the over allocation bar off 

Log in or join to reply