Rough Calculation for manpower requirement
- Created
- 0
- 4
Hi,
I am Pranav Patil, recently I have faced one interview. They asked me to calculate manpower required for a building RCC work whereas building has 4000 Sqm built up area for each floor. Total floors are 30 Nos. Scheduled completion is 15 Month.
I calculated manpower requirement as follows. Please suggest me if I wrong.
Total Nos. of floors - 30 Nos.
Completion time - 15 Months
Cycle time to complete one floor - 30/15 = 0.5 Months = 15 Days.
Carpenter Required
Shuttering work quantum - 4000 x 1.5 = 6000 Sqm (Multiplied by 1.5 for shuttering for beams)
Days to ready slab shuttering = Cycle time / 2 = 15/2 = 7 Days
Per day productivity required = 6000/7 = 858 Sqm
Carpenter + Carpenter helper required = 858 /7 = 123 Nos. (Productivity = 7 Sqm/day/(C+CH))
Barbender Required
Concrete work qunatum = 4000 x0.15 = 600 Cum (considered 0.15 thk of slab)
Quantum of reinforcement work = 600 x 0.1 = 60 MT
Per day productivity required = 60/7 = 8.57 MT
Barbender + Barbender helper required = 8.57/0.15 = 57 Nos.
Total Manpower required:
Carpenter = 123 Nos.
Carpenter helper = 123 Nos.
Bar bender = 57 Nos.
Barbender Helper = 57 Nos.
Concreting helper = 20 Nos.
Mason forfinishing = 2 Nos.
Total Manpower for RCC work = 382 Nos.
Please correct me if I wrong.
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?