Finish date of particular Package got earlier
In the Open Standard
Shreeraj KhilareMember for 9 years 5 months
- Created
- 3
- 4
0
Hi,
Greeting for the day folks,
I was updating one of my program and even after increasing data date by 7 days, finish date of particular package got earlier by 27 days, where my project finish date has increased by 7 days as usual. I have ckecked the links , links seems to be good as this program is in use for 5 years and this is the 1st time something like this has happened.
Please guide me with this.
Thanks in advance.
Shreeraj
3 replies