Hi,

 

Greeting for the day folks,

 

I was updating one of my program and even after increasing data date by 7 days, finish date of particular package got earlier by 27 days, where my project finish date has increased by 7 days as usual. I have ckecked the links , links seems to be good as this program is in use for 5 years and this is the 1st time something like this has happened. 

Please guide me with this.

 

Thanks in advance.

 

Shreeraj

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    it appears that you have over

    it appears that you have over statused your schedule by doing so something else has taken over the critical path

    check your progress again and any constraints 

  2. 0
    Emad Mofarej,PMP,PSP,CDT,CCM ·

    Agreed!Do a float path

    Agreed!

    Do a float path analysis and follow the path link by link and make sure that it makes sense.

  3. 0
    Rafael Davila ·

    I also agree with Zoltan.Make

    I also agree with Zoltan.

    Make sure there is/was no out-of-sequence progress on any update.  If due to "over-statused"/"out-of-sequence-progress" maybe this can give you a clue.

    Out-of-sequence progress is not necessarily a sin, on the contrary it can speed-up a schedule, it can be an improvement on original plan.  I believe out-of-sequence progress shall always be fixed as soon as it happens in order to keep a clear view of schedule logic.

    In any case you shall be in control and understand why it happened.

    Good Luck.