Original duration not showing correctly in primavera

Raja MuruganMember for 9 years 5 months
Created
3
2
0

Hi

Original duration not showing correctly in primavera.

I have assigned 10 hours, 6 days work week calender.

Can anyone one help me?

Raja

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    what is is showing ?what is

    what is is showing ?

    what is the duration TYPE ?

    what is the activity TYPE ?

    What are your settings under your users preferences Time units tab Hours Per Time Period?

  2. 0
    Ghous Mohideen Mohamed Sathik ·

    adminadmin preferencetime

    • admin
    • admin preference
    • time periods

    check your time for hours/day & other

  3. 0
    Zoltan Palffy ·

    Ghous I already said that

    Ghous I already said that 