Rebaselines - BL and Actuals different

Emma ParkerMember for 9 years 11 months
Created
1
2
0

I have rebaselined a project, but for the tasks in progress, the Cum BL Project units are different from Cum Actual Units. Why is this?  Have I got a setting set incorrect, or can I not rebasline when I have tasks which are in progress?

 

Thanks in advance

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    actual unist are based on

    actual unist are based on progress the budget units are static. They will always be different