Acumen FUSE
In the Open Standard
Mohammed ShafiqMember for 19 years 8 months
- Created
- 2
- 4
0
Hi,
I need help in understanding how to upload a primavera xer file into FUSE for the DCMA14 check with an attached baseline. The problem I am getting is, FUSE is showing baseline dates which are totally different to my attached baseline dates in the xer schedule.
I have assigned the baseline to both current project and also the same baseline to the primary baseline but FUSE refuses to pick these dates.
Any help will be appreciated.
Thanks