Acumen FUSE

Mohammed ShafiqMember for 19 years 8 months
Created
2
4
0

Hi, 

I need help in understanding how to upload a primavera xer file into FUSE for the DCMA14 check with an attached baseline. The problem I am getting is, FUSE is showing baseline dates which are totally different to my attached baseline dates in the xer schedule. 
I have assigned the baseline to both current project and also the same baseline to the primary baseline but FUSE refuses to pick these dates. 

Any help will be appreciated. 

Thanks

2 replies

Oldest first
  1. 0
    Thomas Nicholson ·

    I believe you may have to

    I believe you may have to detach the baseline and then import directly into FUSE using the snapshot system.  It's what I do to check for changes from one to the other.  I assume you are exporting the P6 project and if i recall correctly P6 doesn't export the baseline with it or hasn't in the past.

    Hope that helps.

     

    Thom

  2. 0
    Thomas Nicholson ·

    I believe you may have to

    I believe you may have to detach the baseline and then import directly into FUSE using the snapshot system.  It's what I do to check for changes from one to the other.  I assume you are exporting the P6 project and if i recall correctly P6 doesn't export the baseline with it or hasn't in the past.

    Hope that helps.

     

    Thom