About resource Max. Units per time!!!
In the Open Standard
Kuldeep BrahmbhattMember for 9 years 2 months
- Created
- 1
- 4
0
In resources, max units per time means i have to add duration of particular material or machinaries in day or nos of material set or machinaries we are using in a day. Example, If I am using 4 Hydra then when I am inserting hydra as a resource then in Max. units /time cell i have to add duration of hydra using on site or i have to add nos of machinaries per day i am using such as 4/d.
Please give me explanation about it
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?