Labour and Non Labour Unit

Shareeque AcMember for 10 years 8 months
Created
4
5
0

Please help on the Query related to Labour units and non labour units
If I have a particular activity X which can be done with labour as well as machine (e.g.: excavation)
If I have to do same quantity of that activity with labour as well as machine, how can assign labour and non labour units. Because labour may take 10hrs to do that activity where as machine will do in an hour. So there will be different weightage for same activity ..

4 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    just create 2 resources one

    just create 2 resources one labor and one for non labor. The problem lies in where that 1 hour within the 10 hours will be utilized. This is important becasue when the 1 hour is expended this freezs up the machine so that it can be used on another activity. The way to control this is to determine typically when the  1 hour would be used within the 10 hours then assign a resource curve on that resouces based on when the 1 hour will be expended. 

  2. 0
    Vladimir Liberzon ·

    I understood the question

    I understood the question different way. An activity can be done by people in 10 hours OR by machine (excavator) in 1 hour.

    But I did not understand the question itself. If it was about selecting an alternative assignment (use people if an excavator is busy, select the cheapest way of resource assignment, etc.) or what?

  3. 0
    Zoltan Palffy ·

    You asked "If I have to do

    You asked "If I have to do same quantity of that activity with labour as well as machine, how can assign labour and non labour units". I answered this question. But if the question is what do I use manual labor or a machine I guess that depends on the number of machimes that you have an the number of bodies that you have amd how many of the same type activites are being worked concurrently.  

  4. 0
    Mk Tse ·

    For need specified person to

    For need specified person to execute the task, this person is a Labour Type resource, so 10 workers will have 10 resouce items created.

    For need specified machine to execute the task, are machines are in a Non-Labour Type resource.

    If no need to care who are specified (or specified machine) for the piece of works, then the resource type will be "Material"