Window Analysis

Ahmet TuterMember for 13 years 8 months
Created
5
3
0

Can someone give a short and clear description of window analysis? I read a lot of things but still confused. Please do not confuse me with many paragraphs or links etc.... I just need a few sentences clear description if possible.

5 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    you are looking at a spefici

    you are looking at a spefici time frame or period from X date to Y date. Hence the term Window it is a window of time 

  2. 0
    Ahmet Tuter ·

    Yes already I understood that

    Yes already I understood that much actually )

    You look at a specified time frame and do what exactly and what do you achieve?

  3. 0
    Khalid Abdelaal ·

    https://www.udemy.com/delay-a

    https://www.udemy.com/delay-analyis/?couponCode=DELAY111

  4. 0
    Mike Testro ·

    Hi AhmetShort and simple use

    Hi Ahmet

    Short and simple use of Windows Analysis - don't bother because it is a waste of time and useless results.

    If you are going to present a delay analysis by impacting an event on a theoretical critical path then do it once on the whole programme not 12 times on bits of it.

    Best regards

    Mike Testro

  5. 0
    Zoltan Palffy ·

    you can look at a particular

    you can look at a particular time frame where you beleiev that you were delayed and prove your delay during this timeframe. 