Primaver 16.2.5 - importing Global Codes
- Created
- 1
- 2
Its been a while since my last confession:
Can someone explain while Global Activity Codes are not importing with the XER file?
the issue:
Standalone Database in P6 16.2.5 - added new Global codes to the database, updated a schedule with said global activity code then exported file so the Project Manager could manage on his own database. When PM imported the XER he did not get the asigned codes against the activities.
Is there a way when importing to move the activity coding into the Global import sction where you can keep/update the data?
I look forward to the replies.
Festive Greetings
Will