Skip to content

Common Mistakes

Gowhar MirMember for 8 years 5 months
Created
4
5
0

Planners of Planning Planet, what are the most common mistakes/oversights/errors that can be avoided at the begining of planning the prog and might prove to be consequential over the course of the time?

4 replies

Oldest first
  1. 0
    Santosh Bhat ·

    Put some thought into the

    Put some thought into the data structures you want to use in the program, Activity ID's, Coding, WBS naming. You don't want to be making wholesale changes to these down the track.

  2. 0
    Zoltan Palffy ·

    not turning on the times in

    not turning on the times in your program thus 1 day durations span 2 days 

    incorrect data date time

    durations not in whole days

    too many constraints

    missing predecessors

    missing successors

    on the resource calculate cost from units is checked (should not be)

    using incorrect calendars

    resource assignment settings have activity can use the same resource more than once is check (should not be checked)

    durations not set to fixed durations/units/time (if this is not set correctly and you add resources this could change your durations)

    default units per time set to 0 (any thing diivided by 0 is o)

    not correct start date and TIME

    no must finish by date set in program 

  3. 0
    Gowhar Mir ·

    Thanks once again, Zoltan.

    Thanks once again, Zoltan. Can you please tell what can be the effects of

    on the resource calculate cost from units is checked (should not be)

  4. 0
    Zoltan Palffy ·

    you can use this if you want

    you can use this if you want to with the understading that your costs willbe DRIVEB by the manhours multiplied by the cost that you set for this resource.

    i.e cost for the resource is $25/hr you add 4 hours to your units as manhours cost is $100 unless its an engineering function where you have a standard rate this wlll not work.

    if it is set to YES then it wil prevent you from IMPORTING cost from excel since it is set to YES it will ignore the excel import.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?