not turning on the times in your program thus 1 day durations span 2 days
incorrect data date time
durations not in whole days
too many constraints
missing predecessors
missing successors
on the resource calculate cost from units is checked (should not be)
using incorrect calendars
resource assignment settings have activity can use the same resource more than once is check (should not be checked)
durations not set to fixed durations/units/time (if this is not set correctly and you add resources this could change your durations)
default units per time set to 0 (any thing diivided by 0 is o)
not correct start date and TIME
no must finish by date set in program