Resource Assigments. Actual and Forecast, don't add up to Budget?
In the Open Standard
Philip JamesMember for 10 years 6 months
- Created
- 1
- 3
0
Hi
I'm quite new to planning / P6
And have a resource assignments question
I am trying to export the
1. Budgetted Units
2. Actual Units
3. Remaining Units
I go into the Resources Assisgnemrnt Tab and select one of the above and copy the information into excel
However. The units don't add up correctly? I.e
The Actual Units + Remaining Units do not add up to the Budgetted Units figure?
Any ideas?
Regards
Philip
1 reply
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?