Resource Assigments. Actual and Forecast, don't add up to Budget?

Philip JamesMember for 10 years 6 months
Created
1
3
0

Hi

 

I'm quite new to planning / P6

And have a resource assignments question

I am trying to export the

1. Budgetted Units

2. Actual Units

3. Remaining Units

 

I go into the Resources Assisgnemrnt Tab and select one of the above and copy the information into excel

However. The units don't add up correctly? I.e

The Actual Units + Remaining Units do not add up to the Budgetted Units figure?

Any ideas?

Regards

Philip

 

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    unless the job has not

    unless the job has not started or the job is not finished the actual units will NEVER match the budget

    oal of these setting below are made in the Project directory 

    go to the projects directory 

    high light your project 

    click on the calculations tab

    on the right under Resource Assignmenst make sure that under When updating Actual Units or Costs that Subtract Actual from At Completion is checked.

    Also make sure that Recacluate actula Units and Cost whne duration % coplete changes

    Also make sure that Link Actual and Atual This Period Units and Cost is checked

    Also make sure that Link Actual This Period Units and Cost is checked

     

    On the Resoures tab on the right hand side Under Assignmnets Defaults that under Resource Assignments that 

    Resources can be assigned to teh same actviity more than once IS NOT CHECKED

    on the left under Activities make sure that Link Budget and At Completion for actvities not started activites is checked.

Log in or join to reply