Skip to content

Earned Value Help

Debosky WaleMember for 12 years 3 months
Created
1
3
0

Can someone explain to me this situation :

Is it possible to have  dropping  SPI for last 3 periods and the progress actual curve trailing on the slightly above late curve line? The forecast curve continues to show possible improvement starting from the September data period. 

PS, the programme was revised last 3 months with some efficiency introduced into the logic and construction methodology. 

 

1 reply

Oldest first
  1. 0
    Rafael Davila ·

    Earned value method as a tool

    Earned value method as a tool for project control

    4.3. Inferences on future schedule development on the basis of SV i SPI - It is worth remembering that SV ($) and SPI (%) are considered to be measures of time deviation, but they are in fact the measure of difference between the cost of work planned and work done. In practice they are only indirectly and approximately related to the project’s time scale.

    Some of us find EVM flawed for many reasons, just to name a few;

    • It does not distinguish between the works done on critical activities and activities with sufficient floats. A project could be late but EVA will not notice this problem if Earned Value exceeds Planned Value.
    • It motivates project managers to do expensive tasks first delaying cheaper activities that could have higher priorities.
    • The DOD the father of the creature warns against its use on fixed price contracts.
    • Baseline Change Management

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?