P6 Deleted PC User Account

Sonny ValderamaMember for 8 years 10 months
Created
4
4
0

Hi All, The local account I was previously using was deleted due to system update of our IT Team. Unfortunately, I don't have back up files of my projects' schedule. Do you know any way on how to recover or retrieve my schedule from deleted account? Note: I was using P6 R.16.2 in SQLite Standalone database. Thank you and regards, Sonny Valderama

4 replies

Oldest first
  1. 0
    Alexandre Faulx-Briole ·

    Hi Sonny,as you were working

    Hi Sonny,

    as you were working on a stand-alone P6, the project data still were saved in the local database SQLlite; you should be able to install P6 anew and connect it to the existant database, maybe you will need some help from the IT people

    if the SQLlite database was not deleted with your local account, the project data were not deleted either

    Hope it helps

    Alexandre

    P.S. The next time, write your post in the Primavera forum

  2. 0
    Santosh Bhat ·

    SQLite DB's are saved as a

    SQLite DB's are saved as a single file on your PC - if you have backup of this file then you shoul dbe able to recover the database.

  3. 0
    Sonny Valderama ·

    sqlite.db_.pngHi All, Thanks

    Hi All, Thanks for your help. I found something in my PC. I think this is the database file where I established my schedule. The file is dated the day I installed the P6 and created the database. And yes, sorry if I posted on the wrong forum. :)

  4. 0
    Alexandre Faulx-Briole ·

    Sonny,the database file has

    Sonny,

    the database file has the following name: PPMDBSQLite.db; the date shown in the "Modified on" column is the latest date you have used Primavera and thus saved project data in the database; the date shown in the "Created on" column is the date where P6 was installed on the PC

    the file size is closed to 25Mb if the database is empty; mine is 55Mb today

    re-install P6 on the same PC and connect P6 to an "existing database" when required by the install process

    Hope it helps,

    Alexandre