Skip to content

How do you show 3 baselines on one bar?

Philip JamesMember for 10 years 6 months
Created
7
5
0

Hi

My manager has asked me to show 3 baselines on one bar. Shown me the output

 

One bar for one activity, with 3 colours per baseline overlapping to show delay - rather than the usual stack arrangment

7 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    1st maintain and assign 3

    1st maintain and assign 3 baselines 

    then in the gantt area right click bars and select the primary baseline, the seconday basline and the tertiary basline  

    make sure that each of these has their own row number (listed under Pattern) or they may be on top of one another.

  2. 0
    Philip James ·

    Cheers. Oh. The picture isn't

    Cheers. Oh. The picture isn't there... I do want them overlapped I want one bar that goes up to a point with the baseline date, then goes further with the update and to the end with the last update (poorly explained I know)
  3. 0
    Zoltan Palffy ·

    then put them all on the same

    then put them all on the same row number. this is not the correct way to do it but its your call i am just telling you how to do what you want.

  4. 0
    Philip James ·

    Thank you In poorly

    Thank you In poorly explaining it. I know I need to filter the bars....so you can only see the delay
  5. 0
    Philip James ·

    capture.jpg

  6. 0
    Philip James ·

    Worked it out. Filter the

    Worked it out. Filter the bars by PS and CD 

  7. 0
    Zoltan Palffy ·

    glad I could help

    glad I could help 

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?