Rule of Thumb/Best Practice Resource per m2

Mark JamesMember for 7 years 11 months
Created
1
3
0

Hi all

Fairly new to the PP site so apologies if i am posting in the wrong feed.

I am looking to demonstrate to a client that the increase in scope requested without increasing the duration at the work face will cause all sorts of resourcing problems.

Problem is the only information we have at the moment is labour hours and a window of opportunity, no WBS nor sequence of any kind.

My thought is to show a levelled resource against the period of time and then reference a best pratice statement to hopefully show that the resource will be inefficient based on the size of area.

I am sure CIBSE or some other regulation body identify that 1man/30m2 is the most productive but cant find a document that references this. Could anybody point me in the right direction.....?

The project is a large industrial facility and we are installing Building services.

Any help would be appreciated.

Regards 

Mark

1 reply

Oldest first
  1. 0
    Zoltan Palffy ·

    look up top under the tab

    look up top under the tab entitled build times

    there are also several other estimating program but that wokr help you because you need sequence 

    order of operations

    define your activities 

    create the logic

    determine quantities

    based on the quantities and the standard rate of installation determine the duration based on the number of men that you plan to use for that activity.  