EoT (TIA v/s Window Analysis)

Vineet SinghMember for 9 years 10 months
Created
2
3
0

Hello,

Can anyone help  understand the difference in between Time Impact Analysis and Window Analysis for the purpose of Extension of Time and delay analysis.

I have refered to few methods but I feel both were same.  I would appreciate any help in understanding the delay analysis techniques also if i can get the procedure to calculate both.

 

Thanks and regards,

Vineet Singh

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    A TIA is a forward looking

    A TIA is a forward looking prospective schedule analysis technique that adds a modeled delay to an accepted contract schedule to determine the possible impact of a delay to the project completion.

    A Window Analysis is a backward looking or forensic way to look at a delay within a specific "WINDOW" of time. 

    The window analysis is mroe time consuming, more expensive to prepare, require more expertise, more research and preperation time to complete

  2. 0
    Khuong Do ·

    Hi Vineet,You can refer to

    Hi Vineet,

    You can refer to this article : https://doduykhuong.com/2016/09/10/how-to-perform-time-impact-analysis-window-analysis-in-primavera-p6/

    In the last section of article, I address the Differences between Window Analysis and Time Impact Analysis.