There are 2 very important aspects of this
1. From a contractors perspective you can not take away his right to finish early. Finishing early means that his overhead cost will be reduced and he can start on aonther project sooner.
2. Form an owners perspective the specifications usually state that float is jointly owned commodity and shall be used by the project.
in Item #1 what did the contractor do to bring the completion date back sooner ? Was this schedule do able or was it just on paper and did anyone every APPROVE the improved earlier completion schedule ? From your graphic it looks like it was approved.
The Original plan was to finish the project 1 week earlier than the contractual completion.
The Last Accepted schedule was to finish the project 2 weeks earlier than the contractual completion.
Then an event happened what is not clear is whne bouth of the impacts occured. From the graphics it looks like they both happened during the same time frame. In this it would be a concurrent delay on the owner AND the contractor.
Hind sight is 20/20 so what should have been done is the approval of the earlier schedule shoudl have also revised the contractaul completion date and a new line in the sand would have been drawn. Then any impacts would be measured against this NEW date.
Going strictly by item #2 if there was more float created by the earlier completion schedule then this additional float benefits the project and is project owned. NO TIME EXTENSION will be given until ALL of the avaliable float is exhausted. The owner did not request the contractor to finish early he took it upon himself to do so.
Going back to the the original schedule if there was never any earlier completion schedule than what was originally submitted and if the contractor was impacted (by the client) 1 week would there be a time extension ? NO there would not be because the client just used the available float.
Going back to the the original schedule if there was never any earlier completion schedule than what was originally submitted and if the contractor was impacted (by his own doings) 1 week would there be a time extension ? NO there would not be the contractor just used the available float.
So using this same logic with the earlier schedule which is now 2 weeks earlier than the original paln the answer remains the same.
If ANY schedule is pushed out past the ORIGINAL completion date then only that portion which is beyond the completion date would be require a time extension.
It is hard to tell from your graphic but it looks like there is 1 week worth of delay time that need to be analysed.
The way that it drawn there is a concurrent delay during week #2 therefore there should be a 1 week time extension grated but since the 1st week was concurrent and the total delay was only 1 week the time extension would be considered non compensable. So time but no money for extened overhead or extened general conditiions.
The last question is what can be done to bring this date back in line with the original completion date ? Can you fast track the schedule and or crash the schedule ? If so how much will this cost to do and what are the risk factors and the confidence level. to make this happen ?
just my 2 cents