Project duration not reflecting overall original duration

Ayman MohammedMember for 13 years
Created
1
3
0

In the screen shot below, i have applied 7 days work week for project duration activity, start miletone and finish milestone , for all other its 6 days work week calender. On the overall summary level original duration is '959 days' , even though activity project duration is of duration 1095 days. i want to show original duration for project as 1095 days.

1 reply

Oldest first
  1. 0
    Santosh Bhat ·

    Its a function of how P6

    Its a function of how P6 calculates durations for summary bands. If all tasks within a summary band use one calendar, then the summary band will also show duration using that calendar. If there are a mix of calendars, then the summary band will use the project default calendar. So you may want to swtich 5the project default calendar to the 7 day week calendar you are using for the summary activity.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?