Planned Value & Resource Curve
In the Open Standard
Islam Fath El BabMember for 10 years 11 months
- Created
- 7
- 2
0
As per the following below Resource Curve and for an activity of 20 Days Original Duration the Planned Value will be exactly located on last day of the activity.
But for any activity with Original Duration more than 20 Days, the Planned Value will not be located in the last day of the activity.
Please advise how we can get the planned Value exactly on the last day of the activity for those activities exceed 20 Days original duration.
7 replies
Oldest firstLog in or join to reply