wbs in primavera

Craig RobertsMember for 14 years 11 months
Created
4
2
0

Ive imported a msp file into p6 using mpx.

 

I inherited the msp but the wbs went down to activity level.

Ive imported it and the wbs only goes to summary level.

My client will be expecting the wbs to go to activity level like the msp plan he handed over to me to convert.

4 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    2 things1st in the msp turn

    2 things

    1st in the msp turn off the summaries prior to saving the file.

    2nd save the fle in xml format and import the xml into p6

  2. 0
    Sterling Gallagher ·

    Hi Craig There is a new tool

    Hi Craig

     

    There is a new tool available called XerTransfer that will allow you to import easily between both platforms.  The WBS in Both MSP & P6 will match.  It is compatible with Microsoft Project 2013, 2016 & 2019.  You can download a trila version with full functionality in the link https://xertransfer.com/ . As long as you have Microsoft Project 2013, 2016 or 2019 it will be a relatively quick process.

     

    Regards

     

    Sterling

  3. 0
    Celito Graca ·

    Hi Sterling Thanks for the

    Hi Sterling

     

    Thanks for the link. Ive had some problems exporting and importing between MSP and P6 this looks like the solution to my problems.

     

    https://www.profactaplan.com/

  4. 0
    Zoltan Palffy ·

    xer transfer fixes all of

    xer transfer fixes all of this for you 

     https://xertransfer.com/