Hello Everyone,

Need Help.

I saw a schedule in which the Progress is weighed by Cost.

Each activity under each WBS has a cost. So everytime it is updated the WBS shows the % Planned and % Actual.

Overall it shows % Completed based on Cost.

So how can it be set up ?

Regards

Jithin

3 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    1st go to the PROJECTS

    1st go to the PROJECTS directory 

    make sure that your project is open 

    click on the reources tab and at the bottom make sure that resources can be assigned to teh same activity more than once is NOT checked

    go to activites now go to Resources and on the rigth select add

    create an new resource call it lumpsum make sure that calculate cost from units is NOT checked

    filter for all of the activites thet you want cost on 

    select all activities

    right click

    assign resource select LUMP sum

    select file export and export the resource and cost to excel

    populate cost values in excel for each actviity 

    save file 

    import back into p6

    view show on bottom resource useage profile 

    done

  2. 0
    Jithin Kambhikanam ·

    Thanks Zoltan, So by this

    Thanks Zoltan,

     

    So by this each WBS would have its own weightage and overall WBS would show the total progress Planned and Actual ?

     

    Regards

    Jithin

  3. 0
    Zoltan Palffy ·

    yes it will roll up

    yes it will roll up 