Producing Reports from P6
In the Open Standard
Robert CorranMember for 22 years 10 months
- Created
- 4
- 3
0
Good Morning All
I am using P6 v16.2 I cannot get a report out of it formatted as I want it to be, it is a simple report showing planned units for labour and materials, when I export to excelas an xls file the data on each line is one long line of text, why? In all previous P6 applications I have used it has come in as a tabluar report withthe data in the correct columns etc
The way I have got round it at the moment is to take off the file extension, then dump it into wordpad, then import the text back into excel, seems a pointless long winded way of doing things,is there something Iam missing here, a setting somewhere for example?
Any Help would be appreciated
4 replies
Oldest firstLog in or join to reply