Coronavirus impact on the contractuel finish date
In the Open Standard
Abderrahim OUBDIMember for 6 years 8 months
- Created
- 5
- 3
0
Hello,
As you know the coronavirus has been declared as a pendemic. This will affect most of construction projects and will delay the project finish date.
the question is: How can we evaluate the amount of days to entitle to the contractor. Are we going to insert the activity regarding coronovirus in the last revised baseline and then see the effect on the project finish date? or we do this exercice on the last updated schedule ( but we might have concurrent delay, so it we be difficult to identify the only effect of coronovirus)
5 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?