Cable pulling

Anu hansMember for 8 years 11 months
Created
5
4
0

I am looking for advice on output rates for cable pulling. These are internal single core and multicore cables generating from a switch board to various items such as UPS, FANCOIL UNITS, PUMP ROOMS ECT. Can anybody shed some light on  some output rates. For example I have total 10000 metres of multicore cables to  pull. If we assume two pwople gang howmany metres can they pull on a day? Any help will be appreciated

5 replies

Oldest first
  1. 0
    Meng Zhang ·

    10000*0.91/8/2=568

    10000*0.91/8/2=568
  2. 0
    Mike Testro ·

    It depends on if they are a

    It depends on if they are a single cable or in bundles. The actual lenth of the cable is irrelevant.

  3. 0
    Anu hans ·

    They are single cable pulled

    They are single cable pulled from switch board to various places

  4. 0
    Anu hans ·

    Meng,Could you elaborate bit

    Meng,

    Could you elaborate bit on your calculations please?