delay and out of sequence TEST
In the Open Standard
Abderrahim OUBDIMember for 6 years 8 months
- Created
- 1
- 1
0
Hello,
I have done a test updating the schedule at a specific data date (last week):
1- Updating without correcting the out of sequence activities----> result: 32 days of delay
2- Updating with correcting the out of sequence -----> result: 10 days of delay.
Question: Do I have the right to make the correction of out of sequence to meet the actual scenario on the site in order to give an accurate data or I should not make any changes in the current schedule.??
1 reply
Oldest firstLog in or join to reply