Critical Path Analysis

David ZamxakaMember for 18 years 6 months
Created
2
4
0

Hi, everyone

I am managing a project for a client.I have claimed EOT, for the weather delays and the Principal Agent( PA) has asked me to support my claims with the critical path analysis (CPA)using MS Project ,Please Help

Thanks , Regards

David

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    why would not include that

    why would not include that with the original EOT submittal how can you possibly submit a claim without it.

    he wants to see what the critical path was during tha adverse weather. If it was interior work then there would be no impact due to adverse weather. 

    The critical should be expalined in the EOT and should state specifically which weather sensititve were impacted. 