Non Labour Resource - Default Units of Time

J OBrienMember for 8 years 4 months
Created
6
4
0

Hi All,

I have a question regarding a non-labour resource as per the screenshot below:

Resource ID: WAGON BAL 1 represents the ballast wagons that are used to freight the ballast to the rail project site. The price unit for this resource is set at a daily hire rate of $225.00/d in the resources section (I'm unsure as to why it is displaying as $675.00/d in the screenshot).

 

In terms of the resource details, it is set as a non-labour resource (therefore no unit of measure can be assigned), with a 12hrs/7d per week calendar and a default units / time setting of 10.00hr. 

All activity durations within these schedules are hourly (If you're wondering why the original duration in the screenshot is 0.02, it's because there are no labour resources assigned to this activity - they are baked into the unit price of the non-labour resources i.e. train drivers). I will create a dummy resource with no value to enable a 10hr duration to be assinged to the activity.

My question is, even though the resource has been created with a daily unit rate, how can I apply that in the total cost field - for example, 20 wagons x $225.00p/d = total costs of $4500.00?

Cheers,

Jesse

6 replies

Oldest first
  1. 0
    Raymund de Laza ·

    Jesse,Non-Labor Resources has

    Jesse,

    Non-Labor Resources has a unit of measure as time.

    Budgeted Units = 20 Wagons x 12 hrs / day = 240 hrs / day

    Price per Unit = $225 / day  divide 12 hrs / day = $18.75 / hr

    Budgeted Cost = 240 x $18.75 = $4500

     

    Hope this will help.

  2. 0
    Rafael Davila ·

    Staffing and rentals are

    Staffing and rentals are issues a Project Manager must plan and mange.  Staffing and equipment rentals must follow the schedule, usually it is not fixed by pre-determined dates/Time.  Resource schedules are not feasible if not leveled.  Cost of idle resources must be considered within the cost model for it to be reliable.

    Cost-of-idle-resorces-02jpg-Page1

    Cost for Resource A = 7$/hr when idle & 10$/hr when in use.  Resource A availability is 5 ea during the rental period.

    After looking at the schedule resource usage even a rookie PM would schedule to return 2 resources A after Activity 2 finishes.  For such a simple schedule making the descicions is easy, but this is not always the case.

    Resource-Production-01

    Cost-of-idle-resorces-03jpg-Page1jpg-Page1

    Best Regards,

    Rafael

  3. 0
    J OBrien ·

    Hi Raymund,Thanks for your

    Hi Raymund,

    Thanks for your response. I understand that the unit of measure is time based and based on your response it looks like that the 'time' can only be hourly based. I'm surprised that this can't be set as daily time.

    Cheers,

    Jesse

     

     

  4. 0
    Raymund de Laza ·

    Jesse,Time can be set to Day.

    Jesse,

    Time can be set to Day. IN the User Preferences, Under Unit Format set the Time Units and Duration Format to Day.

    Hope this will Help.

  5. 0
    Zoltan Palffy ·

    not true your unit that you

    not true your unit that you are meanuring is durations number of days you said $225 PER DAY

    this is just math

    your duration is 3 days 

    3 days times $225per day =$675

  6. 0
    Rafael Davila ·

    The following references

    The following references might be of interest for those using P6.  I do not use it but at times have to deal with P6 schedules by others, so it is good to know.

    My Settings #02: P6 Duration Unit & Date Format

    Understanding How P6 Works

    Some people like to display durations in days, others in hours.  My preference is to display durations as well as float values in both units as to showcase how durations in days can be so misleading.

    Complex-Calendars

    Float-Days-Vs-Hours

    Best Regards,

    Rafael

Log in or join to reply