Resource unit of measure

Mohamed NizamMember for 19 years 7 months
Created
2
4
0
Is any way to material resource as primary resource Second how to assign of unit of measure such as hour for labor and non--labor Third in resource tab of activity details of update primary resource is any setting to automatically update other resource

2 replies

Oldest first
  1. 0
    Zoltan Palffy ·

    Is any way to material

    Is any way to material resource as primary resource - thats depends on if the # Units of the material is driving the activity

    Second how to assign of unit of measure such as hour for labor and non--labor - yes go to the resource and look under the  

    details tab and there is a drop down there for unit of measure. If you do not see the one you want you can add it by going to Admin then Admin Categories then Units of measure 

    Third in resource tab of activity details of update primary resource is any setting to automatically update other resource

    go to Projects and on the Resources tab under Resource Assignments set the settings there

  2. 0
    Rafael Davila ·

    Agree, when consumable

    Agree, when consumable resources such as raw materials are lacking activities are delayed.

Log in or join to reply