Hi all, Im really struggling with SAP ByD.
Firstly, I can't seem to export a Cost Breadown Structure for all 0 (zero planned Costs). SAPBYD will only export non zero Tasks.
Secondly, SAPBYD, does not recognise any expenses as a remaining Planned Costs. It only views Labour (WORK) as a remaining Planned Cost. I need to do Cost spreading or ETC palnning based on Cost for IFRS15 Revenue forecasting, but SAP does not display any expense ETC.
Has anyone got an answer for me on both topics please?
Regards,
Calvin
Johannesburg, South Africa