SAP Task List Operations

Aaron MorrisMember for 7 years
Created
2
4
0

Hi there,

I've been tasked with reviewing what our requirements are for the creation of new operations within a task list. The below requirements are what we have in our documentation but this has resulted in some tasks having over 100 operations to feed into a Gantt chart. Would really appreciate some improvement suggestions.

An independent operation is any operation which has any of the following differences:

  • Type of work to be performed is different from previous work operation.
  • The resource work centre required to complete the work is different, if not part of the crew already completing the works.
  • Number of hours, or personnel, to complete the work is different.
  • Specific materials or services are required against a specific operation.
  • Specific work instructions are required to be assigned to a specific operation

Regards,

Aaron

2 replies

Oldest first
  1. 0
    Vladimir Liberzon ·

    An independent operation is

    An independent operation is any operation which has any of the following differences:

    • Type of work to be performed is different from previous work operation
    • Work amount (volume) unit is different
    • Resource crew is different
    • Resource productivity is different
    • Material requirements are different
    • Unit cost is different
    • Work calendar is different
    • Dependencies are different
  2. 0
    Aaron Morris ·

    Thanks for the

    Thanks for the feedback Vladimir. I think that certainly helps to clarify the requirement a bit better.

Log in or join to reply