Resource Assignment
In the Open Standard
Michael PetzerMember for 5 years 5 months
- Created
- 5
- 2
0
Hi All,
Need to report 'resource limit' allocated to activities and show on a spread sheet or report. I set up the resources limits as per below, the 'resource usage spreadsheet' still shows the default 8h/d. There are multiple resources (diffrent set limits) allocated to one activity, all showing 8h/d.
Ive tried changing between calendars (resource project), changed settings to set default to 4h/d. Same result as above on the resource and activity spreadsheets.
5 replies
Oldest firstLog in or join to reply