Manhours Calculation for Resource Loading
- Created
- 0
- 5
Dear All
I need some explanation on manhours calculation for resource loading for p6 and MSp
As for my understanding, in p6 the manohurs is called - Budgeted Labor Unit
And for MSp it is called work hour
Quest 1 - Is my understading correct for the above?
Before we come out with the manhours for each activity in the schedule. we must have the productivity for each activity.
Production rate = Qty / unit time
Productivity = manhours / production rate
Estimated manhours = productivity * material qty
Quest 2- Is the above formula correct?
Replies
Oldest firstNo replies yet. Be the first to answer.
Log in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?