Hi Suhaila,
P6 Resources:
1) Labor = Unit (hours)
2) Non-Labor (equipment) = Unit (hours)
3) Material = qty (per unit of measure)
MSProject
1) Work = Type: Work = Hours (labor or equipment)
2) Work = Type: Material = qty (per Material Label or unit of measure in P6)
3) Work = Type: Cost = Cost (expenses in P6)
Input for each Resources and Resources Type:
P6 Resources Assignment:
Depends on the settings of Activity Duration Type:
1) Fixed Duration & Units = Direct input on the Resources Tab - Budgeted Unit (Budget hours/ qty on the task or activity) the duration will not change. Duration Change - Budgeted Unit will not change. Remaining Unit/time - variable and changing based on the input duration or units (Remaining Unit/Time = Budgeted Unit/ Duration).
2) Fixed Duration and Units/Time = Direct input on the Resources Tab - Budget Unit (Budget hours/qty on the task or activity) the duration will not change. Duration Change - Budgeted Unit will change - become variable and changing based on input. Raimaining Unit/time change - budgeted unit will change, duration will not change (Budget Unit = Duration * Remaining Unit/Time).
3) Fixed Units = Direct input on the Resources Tab - Budget Unit (Budget hours/qty on the task or activity) the duration will change. Duration Change - Budgeted Unit will not change. Remaining Unit Change - Duration Change (Budgeted Unit / Ramaining Unit/Time).
4) Fixed Unit/Time = Direct input on the Resources Tab - Budget Unit (Budget hours/qty on the task or activity) the duration will change. Duration change - Budget Unit Change. Remaining Unit/Time change - Duration will change.(Bugeted Unit / Remaining Unit/Time)
MSProject
Depends on Settings of Task Duration Type:
1) Type: Fixed Duration , Effort Driven - Yes (tick) - Duration change - Work units change. Work unit change - duration not change. Resource Unit Change (unit/day) - Duration not change, Work unit change. (P6 equivalent - Fixed Duration & Unit)
2) Type: Fixed Duration, Effiort Driven - No (not tick) - Duration change - Work units change. Work unit change - duration not change. Resource Unit Change (unit/day) - Duration not change, Work unit change. (P6 equivalent - Fixed Duration and Unit/Time)
3) Type: Fixed Unit, Effort Driven - Yes (tick) - Duration change - Work Unit change. Work Unit Change - Duration Change. Resource Unit Change - Duration Change.(P6 equivalent - Fixed Unit/Time)
4) Type: Fixed Unit, Effort Driven - No (not tick) - Duration change - Work Unit change. Work Unit Change - Duration Change. Resource Unit Change - Duration Change.(P6 equivalent - Fixed Unit/Time)
5) Type: Fixed Work, Effort Driven -Yes (always tick) - Duration change - Work Unit no change. Work Unit Change - Duration Change. Resource Unit Change - Duration Change.(P6 equivalent - Fixed Unit)