How do you interpret the wording of these different day count milestones?
In the Open Standard
John ReevesMember for 13 years 5 months
- Created
- 6
- 5
0
If "days count milestones" are phrased differently, how do you interpret:
Submit within five (5) calendar days after NTP0" vs these others. = Start count day "After" ntp?
Submit within 5 calendar days of the NTP0 date. = Start count the day of NTP?
Within 5 calendar days after proceed date in issuance of LNTP. = Start count day "After" ntp?
If it sais to start count at NTP0, but a LNTP is issued (with the next being 1) = are they the same thing and do they have to start the count no matter what it is called?