Liquidated damages do not require the claimate to prove that the loss claimed have actualy been suffered. Liquidted damage clause is used where actual damages though real are difficult or impossible to prove. Its more like therodical damages based on know factors or assumptions.
Howver the contractor must prove how he was damagaed oin a delay situation.
Liquidated damages are calculated priro to awarding the contract. There are 3 things to look at ot see if it is enforceable
1. Is the caluse was reasonable i.e. what assumptions were assumed when determing the dollar amount
2. How were the damages established i.e. what was the basis
3. What was the intent of both parties
I.e. if a train station does not open its not the people who are damaged but the owner of the trains. What is the anticipated amount of ridership that was expected to take that train ? There would be a loss of revenue due to no ridership there and could be extended bussing cost to locations where the train was supposed to go. These are real costs to the owwer/operator.
i.e. You are expected to open the hotel on time but the contractor was late by X number of days. There would be a loss of revenue due to the rooms that could not be rented out.
Not sure whay you mean by what if they accelerate to get the claim who is acclerating the contractor ? He would not accelerate unless he was directed to do so.
He cant or say, if you are not going to pay us we will just drag this out. If he is directed to accelerate then by the terms of the contract he must accelerate and then argure about the cost of acceleration later. If he does not accelerate or come up with an acceleration plan then his contract can be terminated for convienience. The contractor will be put on notice and given 30 days to cure the problem in this case begin the acceleration.
This will allow the owner to unilaterally terminate the contract with or without cause without breach of contract.
If this happens then the owner would go to the contractors bonding company and tell them what happend and that there was X dollars of work remaining when the contract was terminted for convienence. The bonding company would then pay the owner this amount to get another contractor to finish the remaining work.
If breach of contract did not actually impact the project the Liquidated damages usually will not be awarded.