Skip to content

Comparing vs the Approved Baseline vs From the previous month and remaining logic.

John ReevesMember for 13 years 5 months
Created
0
3
0

I am on a project where the remaining logic has the project 20 days behind, but 24 days behind the dates for the same item from the Approved baseline from 8 months prior.  Is the project 20 or 24 days behind?  I would say 20, others say 24.  24 would be more correct for a claim situation, but how often do these really end up in court or arbitration - the 20 is more practical.  In this case its not a big difference - but it can be.  In this case I am guessing calendar complications, but it can be caused by many things.

Replies

Oldest first

No replies yet. Be the first to answer.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?