Indirect Resource Dependency

Alex LyaschenkoMember for 15 years 2 months
Created
4
3
0

Develing examples to demonstrate Volume Lags and Point-to-Point dependencies I have realised that it also could be used to demonstrate indirect resource dependencies.


Reviewed scheduling fragment was with two activities and one dependency. It is easy to imagine real examples when activity A performs preparation for activity B and must be continuously ahead with defined Volume: 20m, 10m3, 10 items, etc.

Technologically, without considering resource requirements, this example looks SIMPLE.

4 replies

Oldest first
  1. 0
    Alex Lyaschenko ·

    Realised that I haven't

    Realised that I haven't shared link to the post. 
    https://saluteenterprises.com.au/indirect-resource-dependency/


    Regards,

    Alex Lyaschenko

  2. 0
    Alex Lyaschenko ·

    Realised that I haven't

    Realised that I haven't shared link to the post. 
    https://saluteenterprises.com.au/indirect-resource-dependency/


    Regards,

    Alex Lyaschenko

  3. 0
    Rafael Davila ·

    Be reminded that

    Be reminded that point-to-point does not means continuous but discrete.

    https://sciendo.com/article/10.1515/otmcj-2016-0013

    • 2.3.5 Continuous precedence relations Hajdu (2015) has also shown that point-to-point relations suffer from the same drawback as end point relations, in that they control only the end points of the fragments ...

    On the other hand Spider Project materials production and consumption can be used to model continuous feed without the end points relations drawback; special materials must be created for any two activities linked this way.

    So easy!

    Continuous-Feed-Model  Hoover and click thumbnail.

    Best regards, Rafael 

  4. 0
    Rafael Davila ·

    Alex,In your post there is a

    Alex,

    In your post there is a link to another post - Point-to-point relationships, the illustration make it easy to understand how to create these links. By far the best I have seen.

    https://saluteenterprises.com.au/point-to-point-dependency/

    A picture is worth a thousand words.

    Best Regards,

    Rafael