Formula for % duration complete
In the Open Standard
Jithin KambhikanamMember for 15 years 6 months
- Created
- 3
- 3
0
Hello All
Need your support in excel.
Need to calculate % complete based on duration consumed from dates with an IFS formula
The table
Start | Finish | 1-Jul-23 | 12-Jul-23 | 15-Aug-23 | 30-Aug-23 | 15-Sep-23 |
10-Jul-23 | 24-Aug-23 | 0% | 7% | 80% | 100% | 100% |
46 |
| Duration Complete | 3 | 37 | 46 | 46 |
Thanks
Jithin
3 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?