Tasks dates not imported in P6

Rox LraMember for 8 years 8 months
Created
1
5
0
Hi all, I am trying to import and MS project file (MPX) to Primavera P6 and after a successful import, the start/finish dates are not imported in P6. If the activity is 100% completed, I only have the A in the start/finish cell in P6. Any thoughts pls?

1 reply

Oldest first
  1. 0
    David Kelly ·

    Rox, P6’s main purpose is to

    Rox,

     

    P6’s main purpose is to calculate start and finish dates.  Specifically Early, remaining early, late, remaining late and planned start and finish. It is a long time since I imported an MPX file, but when importing a spreadsheet you cannot import any of these dates, you can only import dates that are input to the schedule calculations.  To populate date fields in P6 you need to schedule.

Log in or join to reply