Hi,

 

I'm new withing planning, and I can't seem to figure out what the differences between planning qty, earned qty and actual qty is.

 

Example:

Current Budget for welding is 20 760 hours

Plan Qty = 1 810

Earn Qty = 504

Exp Qty = 1696

 

And planned man power is 48, while actual man power was 45.

Can someone please explain to me or give an example of what planned, earned and exp qty is? And what the differences are?

2 replies

Oldest first
  1. 0
    Patrick Weaver ·

    These consepts are derived

    These consepts are derived from Earned Value Management:

    Planned quantity = the amount of the budgeted work planned to be completed in a period, or to date.

    Earned quantity = the amount of the budgeted work actually achieved in a period or to date (measured using the same basis as the budget). In your example ony 28% of the planned work was achieved.

    Actual quantity = the number of welding hours actually booked against the job in the same period or to date..... This activity is a total mess!!  

    For more on this and some free resources see: https://mosaicprojects.com.au/PMKI-SCH-040.php#Overview 

  2. 0
    Joselito Santillan ·

    Planned Qty = 1,810Planned MP

    Planned Qty = 1,810

    Planned MP = 48

    Actual MP = 45

    Exp Qty = 1696

    If 48 (planned) can do 1,810 (planned), 45 (actual) is expected to earn 1696. But you only achieved 504 (actual/earned value). What factor/s have affected your productivity?