Skip to content

What if analysis

Ali HamoudaMember for 24 years 8 months
Created
2
1
0
Hi there,

I wanted to know if we can perform what if analysis in P3 program.

Example:

I have built a program in P3 for a project it is cost 6million KD.

now we are in the first floor Cast roof and columns, and the first roof it supposed to be completed say in 31Mar2002.

the question know what if I finish the first roof in 30Apr2002.

what will be the schedule looks like, or what is the effects(in progress,Cost to complet,..etc.).

How we can perform this analysis?

Answer from Profesionals only would be apreciated.

thanks
Ali
-----------------------------

2 replies

Oldest first
  1. 0
    Ernesto Puyana ·
    Yes you can. In fact, from a project manager’s point of view, that is what Primavera is for.

    Many people see planning and scheduling software only as a rear view mirror - as a tool to register the past: What activities were acomplished, and when. It´s real power lies in the ability to let you look forward and analize the future effect of your decisions today:
    If I apply additional resources (which have an additional cost) to finish a certain activity early, will that result in an early project finish? That’s not always the case, even for critical activities.
  2. 0
    Colin Cropley ·
    Ali
    To perform such a "What-if" analysis, you should make a copy of the current schedule, using the P3 Project Utilities. Then, in the new copied schedule, make the original (current) schedule a target schedule.

    In the layout you wish to modify, apply the changes (such as you described) and re-schedule the project.

    To see how the new "what-if" schedule compares with the original, define a Target Bar in the layout, and place under the Early Bar of the "What-if" schedule.

    You can also define Target 1 Early Start & Finish date columns next to the Early Start & Finish date columns for comparison, as well as Finish & Start Variances (T1EF-EF or T1ES-ES), to quantify how many early or late days the activities will finish or start compared with the original schedule.

Log in or join to reply

ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.

Existing members: your original username and password still work. Forgot password?