Did some one change the links in my program !!!!!!

Ali HamoudaMember for 24 years 8 months
Created
8
5
0
Hello every body,

I would appreciate if some one has a technique or software to enable us to discover any change been made to our original Plan.

Such as change in link, duration,lags...etc.

thanks
Ali
------------------------------

8 replies

Oldest first
  1. 0
    Mike Harvey ·

    Changing links etc

    There is a very good product in the market called project investigator which will interrogate your programme very thoroughly.

    The company is based in the Netherlands - seek advice for full address through your local Primavera dealer.

    Regards
    Mike Harvey
  2. 0
    Mohamed Gebriel ·

    Web Address

    The company is called Primaplan. The project Investigator has a version which works with P3.

    Another tool called Primaplan Flint possibly has the same functions, but theyve got versions of it for P3, P3e and Teamplay.

    The products web addresses are:

    http://www.primaplan.com/products/investigator/investi-index.htm

    http://www.primaplan.com/products/flint/flint-index.htm


    You can download 30-day full working trial versions for both products from the web.
  3. 0
    Mohamed Gebriel ·

    Another SW

    I almost forgot, there is also a sw called digger from a company called HST Software.

    Their web address is: HST Software
  4. 0
    Forum Guest ·
    Another company produces P3 comparison software with analysis tossed in as well called Schedule Analyzer. Look to www.ronwinterconsulting.com for more.
  5. 0
    Soheil Jafari ·
    Hi,
    Digger is the powerful SW.
    Please do not miss it.
  6. 0
    Jorge Taguinod ·
    If you dont want people to make unneccessary changes in your program, you can also take advantage of P3s security.

    However, be forewarned that theres a way around this security and thats by someone giving himself Privileged rights in Netset.

    The safest way is to backup your files and store these in a safe place. Only the paranoid survives.

    Jorge
    Crown Systems (Philippines)
  7. 0
    Zq qz ·
    Hey Guys and Kabayan ,
    To deterimine if some one change or some changes has been made in your schedule specially relationship.yes Primaplan ,digger is effective but if your familiar with Microsoft access database you can make your own schedule checker.to do it for your.
  8. 0
    Anonymous ·
    I agree with the last comment, use Access to check for differences between shedules. Digger has had difficulty with a number of my schedules in the past and I always end up returning to Access. Just be sure you understand what each of the field definitions mean - they arent very user friendly.

Log in or join to reply