Durations in P3
In the Open Standard
Forum GuestMember for 17 years 8 months
- Created
- 4
- 3
0
Can anyone help please !! I have just started using P3 and could do with a little advice. I have various activities that happen in series being performed by one resource, the problem is the duration are in fractions of hours.. So on the original duration column I am putting in an hour as it will not accept fractions and for the resource I am putting the fraction as the units per hr and budgeted quantity, I have tried putting 60 units per hour and budgeted quantity as a fraction but it will not accept it.
Can anyone tell me the best way to display this information.
Can anyone tell me the best way to display this information.
4 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?