% complete
In the Open Standard
Forum GuestMember for 17 years 8 months
- Created
- 9
- 3
0
Hi All
This question is about controlling the progress of the project,I believe that three things have to be updated,
1)actual todate(or this period),2)ETC estimate to complete
3)remaing duration,4)% percent complete.
Kindly I need to confirm from your experience that those are the only items to update,and If I am updating using mhrs,which % complete to use? is it the physical quantity
divided by the budgeted quantity,example 10meter out of 100meter(quantity) and therefore I insert 10% as percent complete,or I look how many manhours spent against total,example 30hrs out of 100 and thus 30% which is physically wrong since on site I am only progressed 10%.
Thanks in advance.
AA
This question is about controlling the progress of the project,I believe that three things have to be updated,
1)actual todate(or this period),2)ETC estimate to complete
3)remaing duration,4)% percent complete.
Kindly I need to confirm from your experience that those are the only items to update,and If I am updating using mhrs,which % complete to use? is it the physical quantity
divided by the budgeted quantity,example 10meter out of 100meter(quantity) and therefore I insert 10% as percent complete,or I look how many manhours spent against total,example 30hrs out of 100 and thus 30% which is physically wrong since on site I am only progressed 10%.
Thanks in advance.
AA
9 replies
Oldest firstLog in or join to reply
ProjectControls.com is free to join. Members can post questions, reply, vote and follow discussions.
Existing members: your original username and password still work. Forgot password?