Data Export

Forum GuestMember for 17 years 8 months
Created
4
1
0
Please could anybody tell me if it is possible to export individual project data dates from a Project Group?
I have tried using the report writer in the Project group but it specifies the Group data date only for all Sub-Projects. Any Ideas???
I am trying to create a Group report which identifies when a sub -project was last updated.

4 replies

Oldest first
  1. 0
    Steven Oliver ·
    How about creating a Custom Data Item (type = start) in each of the subprojects use a global change to set the value of the CDI = Data Date.

    Bit long winded but it works. If I remember right you can also use PRMBatch, but I dont have the manual (or the CD).
  2. 0
    Mk Tse ·
    In option, uncheck overwrite sub-project data date when scheduling.
  3. 0
    Jorge Taguinod ·
    Hi Forum Guest,

    1. First, make sure that your setting allows for multiple project data dates.

    From the menu, select: >Tools >Schedule> Options
    Select Advanced Tab
    Remove check from "Project Group Scheduling"

    2. Run the schedule with the Schedule Statistics Report.
    From the menu, select: >Tools >Schedule >Schedule Now.
    Note: Do not use F9 as this doesnt bring out the Report.

    You will see in the report that the different projects in the project group will have different project start dates, project finish dates, data dates, etc.

    Hope this helps.

    Best regards,

    Jorge
  4. 0
    Forum Guest ·
    Thanks Jorge

    What you`ve said will suffice for my purpose although I was hoping for a simpler report.
    I can still utilise excel to give me what i need in the way of a simple report.